Columns compare weekly demand and output; the line is week-end stock against the MIN–MAX corridor (solid band = defined in the MPS, dashed = last value extended). Each item shows two plans — A: strict MIN/MAX execution (halt when above MAX, fill to MAX at best, whole-day scheduling, 6-day peak weeks — 500L 400/day, M/S 1,100/day — CNY idle): the red GAP marks demand we cannot serve; B: current pre-build rhythm — our proposal. The strip below each chart shows production days per week. Daily rates 日产能: 500L 300/day standard, 400/day at full stretch when closing the gap; the shared M/S line 800/day off-season, 1,100/day at the peak. 柱状图对比周需求与周产出;折线为周末库存对照 MIN–MAX 区间(实线段=MPS 已定义,虚线段=末值延伸)。每款两个方案——A:严格按 MIN/MAX 执行(超 MAX 停产、最多备到 MAX、整天排产、旺季 6 天——500L 400 套/天、M/S 1,100 套/天——春节放空):红色 GAP 即无法满足的需求;B:当前节奏备库存(我方提案)。图下条带为每周生产天数。日产能:500L 常规 300 套/天、追缺口时拉满 400 套/天;M/S 共线淡季 800 套/天、旺季 1,100 套/天。Bottom line: strict execution (PLAN A) loses ~66,000 pcs of 2027 sales by W20 — 12,480 on 500L (deepest 27W07) + 53,544 on the shared M/S line (deepest 27W14, after the W13 spike). 合计:严格执行到 27W20 将损失约 66,000 件销售(500L 最深 27W07,M/S 共线最深 27W14——W13 尖峰之后)。
Is the 2026 plan conservative or aggressive? Each bar is the cumulative 2026 W1–W52 demand, split into firm demand and forecast; the red tick marks the 2025 full-year actual. 每条为 2026 全年累计需求,分实单与预测两部分;红色刻度线为 2025 全年实际——高于红线即计划高于去年。
For MTO we hold no MIN/MAX — stock exists only to bridge demand peaks above weekly capacity. Wherever the line touches zero (or goes red), the pre-build window before it is the order deadline. MTO 不设 MIN/MAX,库存仅用于削峰。The dates under each chart are when we must lock each build — and with only 2 weeks of demand frozen today, every one of them is committed on forecast alone, at our risk. Hence ask 04 below: freeze 4 weeks instead of 2. 各图下的周次是我们必须锁定排产的时点——目前只冻结 2 周需求,这些备产全部押在预测上、风险自担。对应下方诉求 04:冻结期 2 周 → 4 周。
Building stock is our decision and our risk — we will run the 6-day peak from W41/W44 and pre-build per PLAN B at our own cost, as shown above. What helps us most is visibility. 备库存是我们自己的决策与风险——我们将按 PLAN B 自担成本备货(W41/W44 起满产),上文已透明展示。最能帮到我们的,是可见性。
The new W23–W39 band (MAX 4,214 / 5,915 / 8,767) sits below today's stock and, strictly executed, forces production halts of 6–8 weeks (PLAN A) — a factory cannot sustain minimum operation that way. The pre-W23 levels (12,396 / 23,855 / 11,749) kept us workable: please restore them.
新的 W23–W39 区间(MAX 4,214/5,915/8,767)低于当前库存,严格执行须停产 6–8 周(见 PLAN A)——工厂无法维持最低运营。W23 前的水平(12,396/23,855/11,749)是可运转的,希望恢复。
The 2027 W1–W20 peak needs year-end pre-builds of ≈21,000 (500L) / 52,000 (500M) / 16,500 (500S). We carry the build cost and risk — PLAN A shows the alternative loses ~66,000 pcs of 2027 sales.
2027 年 W1–W20 高峰需要年末备至约 21,000 / 52,000 / 16,500。建库存的成本与风险由我们承担——PLAN A 已显示不备的代价约 66,000 件。
If the change lands in the off-season — i.e. now — the supply-chain impact is minimal: stocks are at their yearly low and the 2027 pre-build has not started. Once we start building (W41/W44), every week of delay puts more old-colour stock at risk.
若换色落在淡季(也就是最近),对供应链影响最小:目前库存处于全年低位、2027 备货尚未开始。一旦 W41/W44 开始建库存,确认每晚一周,旧色库存的风险就大一分。
Demand spikes arrive with little warning, yet only 2 weeks are frozen today — inside our build lead time, the plan cannot react. A 4-week frozen window lets us schedule against committed demand instead of forecast.
需求时有突增,而目前只冻结 2 周——在备产提前期之内,计划来不及反应。若能锁定 4 周需求,我们就能按确认需求排产,而不是押预测。
ESS 100 and TRA 500 are 2026 launches with no history to simulate — beyond your forecast they are blank. And every MTO build date above is locked on forecast alone: the earlier and more reliable it is, the less risk on both sides.
ESS 100 与 TRA 500 为新款、无历史可模拟,预测结束即空白;上文每个备产锁定点都押在预测上——预测越早越可靠,双方风险越小。